fbpx

Results sharing

Dam Structure Grout leak-Proofing Case 

uol namoro cidades do ma Dam Structure Grout leak-Proofing Case  Reinforcement Technology for Complex Dam Leakage 1. BACKGROUND Dam Structure Grout leak-Proofing Case :A dam spillway gate rail groove, diversion pier wall, sand discharge channel water retaining end wall, etc., had different forms and scales of leakage. In order to maintain the long-term use safety of the dam, the management unit

STRATUM GROUT

STRATUM GROUT CURTAIN REINFORCEMENT CASE

citas online coopesiba STRATUM GROUT CURTAIN REINFORCEMENT CASE – Grout curtain reinforcement technology in reservoir water tunnel fractured rock zone. 1.PROJECT BACKGROUND STRATUM GROUT CURTAIN REINFORCEMENT CASE: An additional water conveyance tunnel at a reservoir was connected to an existing water diversion tunnel. In the inclined pipe section, there was a region of about 9.5m of fractured rock,

Swimming Pool Damage Investigation and Repair Technology

Grout : Pool leakage Grouting Repair Case-Swimming Pool Damage Investigation and Repair Technology

http://ambiance-verandas.fr/?tamagochi=recherche-sage-femme-en-le-lude&eb6=83 Grout : Pool leakage Grouting Repair Case-Swimming Pool Damage Investigation and Repair Technology 1.  PROJECT BACKGROUND Grout : After a university swimming pool was in use for a period of time, localized cracking, water leakage, and mud inflow around the water inlet occurred. In order to restore the swimming pool to normal use as soon

Airport taxiway subsidence composite reinforcement repair technology

Ground Improvement : Airport Taxiway Subsidence Composite Reinforcement Repair

rencontre gay choisy le roi Ground Improvement : Airport Taxiway Subsidence Composite Reinforcement Repair Technology-The Most Effective Way to Improve and Reinforce Airport Taxiway Pavement Subsidence 1. PROJECT BACKGROUND Ground Improvement : After a period of use, an airport taxiway experienced localized continuing subsidence, resulting in flexible pavement cracking. In order to prevent accidents, the operators, especially invited industry experts to

Grouting : Water Stop Reinforcement of Ground Strata at MRT Station

Grouting : Water Stop Reinforcement of Ground Strata at MRT Station TBM Arrival Abandoned Shell Section-Confined Space Double-Tube Grouting Case 1. PROJECT BACKGROUND Grouting : A TBM was digging to the front of a diaphragm wall of a new MRT tunnel underground station. Due to the complex ground strata conditions and the abnormal pressure of

Grouting Case : Sloping Site Building Raft Foundation Water inrush Hot bitumen Repair Technology

Grouting Case : Sloping Site Building Raft Foundation Water inrush Hot bitumen Repair Technology-The Most Rapid and Effective Repair Technology for Serious Water Leakage in Foundation Slab and Side Walls of Building on Sloping site. 1.PROJECT BACKGROUND Grouting Case : There were two high-rise SRC buildings in a large-scale hillside development project. Four basements were

WATER INRUSH STOP HOT BITUMEN GROUTING TECHNOLOGY FOR SEDIMENTARY SOIL LAYER EXCAVATION SITE

Grouting Case : Sedimentary Soil Layer Excavation Site

Grouting Case :Water Inrush Stop Hot Bitumen Grouting Technology For Sedimentary Soil Layer Excavation Site -A rapid and effective leak-stopping method for deep pit excavation with a large volume water inrush 1.PROJECT BACKGROUN- Grouting Case : The site is adjacent to the MRT main line and elevated roads, and it was being constructed by the

Grouting Case : Airport Taxiway Grouting Reinforcement & Mud-Spray Treatment

Grouting Case : Airport Taxiway Grouting Reinforcement & Mud-Spray Treatment Technology-The Most Rapid, Effective Method For Filling & Strengthening Ground Beneath Paving Slabs 1. PROJECT BACKGROUND Grouting Case : In the rainy season, an airport taxiway had serious mud spray from expansion joints and paving slab cracks. In order to avoid hazards such as foundation

Tunnel

Tunnel Access Shaft Sidewall Water Inrush Blocking Technology

Tunnel Access Shaft Sidewall Water Inrush Blocking Technology——The most effective method to stop water inrush in shaft excavation. 1.PROJECT BACKGROUND When a drainage tunnel was being excavated near the bottom of an access shaft, an inrush of high-pressure fissure water was encountered at the rock formation/fracture zone joint plane.  The water output was more than 3.0m3 per

TBM Shaft

TBM Shaft Horizontal Grouting Site Improvement Technology

TBM Shaft Horizontal Grouting Site Improvement Technology——The Most Effective Site Improvement Technology to Avoid Impact With Shallow Obstacles. 1.PROJECT BACKGROUND TBM : The capital of Thailand, Bangkok, is located on a sedimentary plain with an average elevation of about 2m. The Chao Phraya River runs through the urban area. It is often troubled by floods