fbpx
           

Airport Taxiway Subsidence Composite Reinforcement Repair Technology

Airport taxiway subsidence composite reinforcement repair technology

Airport Taxiway Subsidence Composite Reinforcement Repair Technology-The Most Effective Way to Improve and Reinforce Airport Taxiway Pavement Subsidence

1. PROJECT BACKGROUND

stringently After a period of use, an airport taxiway experienced localized continuing subsidence, resulting in flexible pavement cracking.

mujeres solteras en santa marta colombia In order to prevent accidents, the operators, especially invited industry experts to study repair countermeasures.

Giarre The airport was not only a taxiway, but aircraft take-offs and landings were frequent, so the repair project required completion within a time limit to reduce the flight delays.

某機場跑滑道於使用一段時間後局部發生持續性沉陷,並造成柔性鋪面開裂現象機起降頻繁,修復工程要求限期完工,以降低航班延誤情況發生

 

 

 

 

 

2. SOLUTION

According to the study findings, the main causes of the airport taxiway subsidence were: the compaction of the roadbed soil layer in the subsidence sections causing slight voids and cracks in the cement treatment layer under the road slab.

In the rainy season, the soil under the roadbed was subjected to surface water infiltration.

When subjected to the concentrated load of wheels, the mud sprayed up to ground level through the fissures, causing localized hollowing out.

Therefore, in solution design, special emphasis was placed on the improvement of the roadbed soil and the cement and jacking and strengthening treatment.

 

 

 

 

 

 

 

3. WORKS DESIGN

Due to the tight repair period, in addition to the 24-hour uninterrupted planned works, the selection of grouting materials was especially long-lasting grout with high compressive strength and short setting time.

To improve the roadbed soil layer, non-shrinking cement LW grout to be used; at pressure of not more than 3000kPa, and the vertical jacking height not less than 3mm.

For cement treatment of underlying layer reinforcement grouting, non-expanding rigid PU resin grout at pressure of not more than 1000kPa, and the vertical jacking height not less than 3mm.

基土壤地盤改良採用無收縮水泥LW漿材,灌注壓力不大於3000kPa,垂直頂昇高度不小於3mm水泥處理底層加固注漿採用不膨脹剛性PU樹脂漿材,灌注壓力不大於1000kPa,垂直頂昇高度不小於3mm。注漿材料選擇時,特別以抗壓強度較高、固化時間短的長效性漿材為主

 

 

 

 

4. WORKS PROCESS

The aggregate asphalt layer and the modified density asphalt layer on the surface of the repaired section was to be milled and planed later, so during site improvement and reinforcement grouting, it was required to achieve effective jacking conditions in order to fill voids and form the compaction grouting. 

In order to control the overall jacking amount and at the same time to make the injected grout evenly distributed under the taxiway, the grouting process used an auto-alarmed laser level with an accuracy of 0.5mm for multi-point recording and control.

In order to emphasize work efficiency when drilling, a pneumatic drill was selected for deep hole drilling; an electric long drill was used to perform shallow hole drilling.

All large-scale equipment was installed on motorized vehicles to coordinate with airport security.

確實填充地層空隙及形成壓實注漿(Compaction Grouting)效果灌漿過程採用精度0.5mm的自警式雷射水準儀進行多點記錄與管控採用氣動式鑽孔機進行深孔鑽進;電動長鑽孔機配合執行淺孔打設

 

 

 

 

5. RESULTS

In order to achieve excellent site improvement and reinforcement effects, an automated control system was used for pressure and flow control, and recording during the grouting process.

Through the uninterrupted efforts of all the staff and supervisors, all the grouting work was successfully completed and within the time required by the contract.

After the supervising group confirmed that the design requirements were exceeded, the site was handed over to the construction unit to re-lay the asphalt surface.

The composite reinforcement and repair work for the subsidence of the airport taxiway was successfully completed.

採用自動控制系統進行壓力與流量調控與紀錄

本工程順利於契約要求時間內完成所有灌注工作

 

 

 

 

 

 

More Construction Result Sharing

・Follow up our FB for news

Contact us:+886 2769-2355

Airport Taxiway Subsidence Composite Reinforcement Repair Technology

Un Get the full PDF by filling up your email
FREE DOWNLOAD

Send download link to:

Copyright ©Jines Construction Co.,Ltd

Add a Comment

Your email address will not be published. Required fields are marked *